During the week of August 27th, downtown infrastructure work will continue along the westbound lane of Park Avenue, SW moving towards Laurens Street. Work will also begin on the northbound side of Laurens Street between Park Avenue and Richland Avenue. A second crew will begin working along Hayne Avenue by August 31st. Continue to watch for any lane closure signs. Businesses and residents will be notified prior to interruptions of water services, if any.
Park Ave STA. 14+75 (I-41) – New Structure I-41; Existing 12” clay pipe (right) and new 8” RCP (left) grouted within structure. (8/20/18)
Park Ave STA. 14+75 (I-41) – New Structure I-41; Existing 12” clay pipe (right) and new 8” RCP (left) grouted within structure. (8/20/18)
Park Ave and Newberry St northwest corner (I-42): Concrete curb and gutter formed and installed (8/20/18)
Park Ave and Newberry St northwest corner (I-42): Concrete curb and gutter formed and installed (8/20/18)
Park Ave STA. 14+50 – Fire hydrant tapping sleeve and valve (TS&V) installed and pressure tested (08/21/18).
Park Ave STA. 14+50 – Fire hydrant tapping sleeve and valve (TS&V) installed and pressure tested (08/21/18).