Today, November 15, work commenced on Phase 1A of the Newberry Street Water and StormWater Utility Infrastructure Improvements.  The City of Aiken consulted with Johnson, Laschober, & Associates, PC (JLA) to perform the scope of services and project description, and provide construction administration and resident project representative services for this project.

Daily work hours are currently Monday – Friday from 7:00am to 5:30pm.  Additional schedule notes are as follows:

  • Prior to today, a CCTV camera was used inside the storm sewer to verify the condition of the pipe and buried manhole
  • Starting Nov. 15: the process of spin-casting the storm sewer (trenches construction with no excavation required)
  • End of November: Open-cut excavation at Park Ave. for tap into existing water main.

The City of Aiken would like to note that no work will be performed during events being held in the Municipal Building or on Newberry Street and The Alley.  The above listed primary schedule and working hours may be subject to change.